1- Vessel should be water carrier tanker with around 6000 MT capacity.
2- The cisterns of this vessel as the reservoir should be made by composite
material.
3- Fresh water production 3000 MT/24 hrs continuously.
4- Desalination, R.O system containing the machinery for Disinfectant and
making the water as the Drink water.
5- Bottle maker for 1.5 Lt,4 Lt,20 Lt with production capacity of : (55000 /20
Lt, 275000/4 Lt, 700000/1.5 Lt)/day.
6- Bottle filler machines, around 2000 MT/day.
7- Packing system.
8- All necessary accessories.
9- from the signing the MOA to lunching the vessel should takes time utmost 6
months .
10- The client are very serious and looking for the best quality and the good
price.
11- He accepts the ZC calcifications, if it could be changed to IRS class.
|